Revised: March 12, 2010
Tentative Agenda
UNOLS FLEET IMPROVEMENT COMMITTEE MEETING
University of Southern Mississippi
Department of Marine Science Facility
NASA's John C.
Stennis Space Center
Day 1: Monday, March
29, 2010
0800 Coffee and
Pastries
0830 Call the Meeting: Clare Reimers, FIC Chair, will call the
meeting to order, introduce the new FIC members, and provide an opportunity for
introductions around the room.
·
FIC Membership
Discuss the terms that will expire in 2010
0845 Reports
on Research Vessel Design and Construction Efforts
·
0845-0915: Regional Class Research Vessel (RCRV): Down-select decision, FY 2010 & 2011 Plans, FIC
Tasking in preparation for Phase I Project Refresh - NSF
·
0915: Ocean Class Research Vessel (OCRV):
−
Design/construction
team selection Chris MacDonald and Mike Prince
−
Status
of Operator Selection Mike Prince
−
Ocean
Class Advisory Committee (OCAC) timeline, constraints, status
−
Uncontaminated
Seawater Systems Mike Prince and Maureen Conte
−
FIC
Tasking?
−
OCRV
SMR Document Update - Jon Alberts
·
1000: R/V Sikuliaq - Alaska Region Research Vessel
(ARRV): Marc Willis
−
Status of construction
−
How is the ARRV
different from the two Navy OCRVs?
·
1035: Fleet
Utilization, OOI ship time projections Annette DeSilva
·
1050: Issues before RV operators and technical
support groups
−
RVOC - Al Suchy
−
RVTEC Marc
Willis
−
Projected Service
Life End Dates
−
Aging Vessels Is
there a need for a pool of long-lead time spare-parts pool?
−
Shipboard Noise
in labs and accommodation spaces
·
1145: UNOLS Council
and Committee Activities of Interest to FIC UNOLS Office
1200 Lunch Break
·
1300: RV Hugh Sharps debriefs: What we have
learned so far from a modern RCRV, how to proceed with the debriefings) Clare
Reimers
·
1320: RV Kilo
Moana Load handling system - Status report on the installation of the new
Load Handling System. Clare Reimers
1345 Evaluation of possible platforms to support
NSF's Long Core System - Currently Knorr is the only ship in the UNOLS
fleet configured to deploy the long core system and Knorr is slated for its end of service life in 2015 as per the
Fleet Status Report. - Al Suchy
1430 Global
Class Planning
·
Status of NRC
recommendations
·
Approaching a
multi-agency solution to Global ship replacement (can we think out of the box?)
1500 Fleet
Improvement Plan (FIP): Clare Reimers
·
Follow up on FIP recommendations
·
Appendix
on Ocean Acoustics
·
Future FIC
meetings before or after the Council meeting?
1550 Review and Update FIC Action/Task List from
the October meeting Clare Reimers
Day 2 Tuesday, March 30th: Joint session of the FIC and Council
0800 Coffee and
Pastries
0830 Call the
Meeting: Vernon Asper, UNOLS Chair, will call the
meeting to order and provide an opportunity for introductions.
0845 UNOLS 2010 Fleet schedules and science
operations, estimated operation costs, and 2011 ship
scheduling Jon Alberts and Liz Caporelli
0915 Agency Reports Budget projections, ARRA
funding review, facility renewal efforts, agency initiatives:
·
NSF Bob Houtman
o
Equipment Pools Vans, winches, and
wire Matt Hawkins
·
NOAA
·
NAVY Tim
Schnoor
0945 Summary of Fleet Improvement Committee
Meeting and Action Items Clare Reimers
1000 An Ocean Infrastructure Strategy for U.S.
Ocean Research in 2030 The National
Research Council has formed a committee to provide advice on the
types of U.S. ocean infrastructure that will facilitate research in 2030. The project scope and committee membership
can be viewed at http://www8.nationalacademies.org/cp/projectview.aspx?key=49139
. Peter Wiebe
1020 Break
1040 Interagency Working Group on Facilities Report on the IWG-F
activities and plans
1055 Consortium
for Ocean Leadership Report on
Ocean Leadership items of interest
to UNOLS.
1110 Greening
of the Fleet Bruce Corliss
1200 This concludes the joint meeting of the FIC
and Council.