Status of the "Top Ten"

Shipbuilder Accepted Responsibility for Delay in Launch and Delivery

As Consideration, We Negotiated a Contract Change to Accomplish Much of Our "Top Ten"

The Following Have Been Incorporated Into the Contract and will be Accomplished Prior to Delivery

  • Increase area and bench space in labs
  • Improve traffic flow
  • Reduce science freezer
  • Relocate dive locker
  • Fantail wet lab
  • Choices for vans
  • Stowage for on-ice equipment
  • Area for incubations
  • Portable lab refrigerators and freezers
  • Will Test Lab Temperature Controls and Sea Water Temperature Monitor and Controls on Trials

    Data Archiving is a Procedural Issue which can be resolved by Discussion with Coast Guard Representatives

    Bridge Wings Designed and will be sent to Panama Canal for Approval

    Schedule

  • Start Construction March 1996
  • Keel Laying September 1996
  • Launch November 1997
  • Crew, Phase 1 & 2 May/June 1998
  • Delivery December 1998
  • End Navy Responsibility/Funding January 2000
  •