APPENDIX III
Captain Johnson's HEALY Slides
Photocopies of the slides illustrating construction of the HEALY are at theUNOLS
office.
Status of the "Top Ten"
Shipbuilder Accepted Responsibility for Delay in Launch and Delivery
As Consideration, We Negotiated a Contract Change to Accomplish Much of Our
"Top Ten"
The Following Have Been Incorporated Into the Contract and will be Accomplished
Prior to Delivery
Increase area and bench space in labs
Improve traffic flow
Reduce science freezer
Relocate dive locker
Fantail wet lab
Choices for vans
Stowage for on-ice equipment
Area for incubations
Portable lab refrigerators and freezers
Will Test Lab Temperature Controls and Sea Water Temperature Monitor and Controls
on Trials
Data Archiving is a Procedural Issue which can be resolved by Discussion with
Coast Guard Representatives
Bridge Wings Designed and will be sent to Panama Canal for Approval
Schedule
Start Construction March 1996
Keel Laying September 1996
Launch November 1997
Crew, Phase 1 & 2 May/June 1998
Delivery December 1998
End Navy Responsibility/Funding January 2000