We are asking for your input to help formulate the UNOLS response to NSF on setting priorities and perhaps narrowing the requirements in an effort to help meet the goals of reducing acquisition and operating costs. NSF has identified their goals in terms of a total acquisition cost of $25 million dollars and a day rate in the neighborhood of $10,000 per day ($2 million/year for 200 day operating year). This is somewhere between the cost of current Regional Class vessels and current Intermediate Class vessels.
The preliminary development of the Regional Concept Design by JJMA in Phase I & II of their feasibilty studies has shown that a mono-hull vessel of approximately 1,150 tons displacement (176 ft LOA) can meet all of the Regional Class SMRs, as can a SWATH vessel of approximately 1,300 tons displacement (149 ft LOA). The mono-hull is estimated to cost over $13K/day and the SWATH over $14K/day. Acquisition costs for these size vessels would exceed the $25M by several million. Smaller vessels can be designed, but this may require compromise on some of the important SMRs.
Preliminary Phase III study information is contained in a report from JJMA.
Phase II of the Regional Class Design Study reports and background on the SMR's can be found at:
For a table of comparative data on these "major impacts" SMR parameters for existing ships (deck space, lab space, etc.), click here.
NSF would like to make these decisions with input from the community and we would appreciate receiving your answers to some questions, some rank ordering of certain SMRs and your comments. Please use the form below for this purpose. For each high impact SMR the published requirement is shown in the right hand column for your reference as needed. In the left column there is a summary of issues related to the SMR element from the JJMA study followed by a couple of questions and a comment block. At the end the end of the form we ask you to rank order certain SMR elements against each other. Lastly, you may provide any general comments regarding the high impact SMRs, medium and low impact SMR's identified in the JJMA report or on the Regional Class design in general.
If you do not have time to go through the entire form, please take the time to complete the rank ordering questions and provide a quick comment at the end of the form. The information in the JJMA report and below should help define the issues for you.
Science Berths |
Published Requirement |
|||||||
Berthing related issues that directly impact vessel size and cost:
|
Accommodations: 16 to 20 non-crew personnel | |||||||
| A minimum of 16 non-crew personnel
in two-person staterooms is required and it is highly desirable to have
the capacity to carry 20 or more when needed. Total complement
would include an adequate number of maritime crewmembers to support the
scientific mission, meet regulatory requirements, and support the need
for proper maintenance of the vessel. The ability to accommodate up to
40 non-crew personnel safely on day trips should be included in design
and outfitting decisions.The non-crew personnel (often referred
to as the Science Party) would consist of the personnel from the various
scientific programs, the assigned marine technicians, technical support
personnel for certain types of instrumentation (e.g. ROV/AUV groups, OBS
groups, coring groups, etc.), foreign observers, education, and outreach
personnel, and anyone else not part of the maritime crew.The
vessel should be designed for optimum habitability for normal science
party size with the ability to expand to larger science party sizes when
needed. Supporting infrastructure would be designed around the largest
possible complement. Shower and toilet facilities should normally
support no more than four people per unit. Staterooms should
be designed to optimize the available space while maximizing habitability.
Providing basic storage, washbasins, and limited workspace should be attempted
in the design. Additional storage and larger workstations could be provided
in common space elsewhere. Provisions should be made to accommodate
gender imbalance. The concept for designing a surge capacity that can be effectively used when needed is important to the flexibility of these vessels to support a wider range of potential projects. Making space such as a lounge or conference room convertible to bunk space or other effective use of space should be considered. The use of vans could be considered as long as the resulting accommodations are integrated into normal ship services, and they can be safely utilized. Past failures involving the use of berthing vans should be avoided. The maritime crew and resident marine technicians should be berthed in single person staterooms to the maximum extent possible in order to promote crew retention and the resulting expertise for supporting the scientific mission. |
||||||||
QuestionsWhat should the minimum number of permanent berths be? How many surge capacity berths are needed? Can surge berthing be multi-occupant (more than two person)?
Should vans be used for berthing?
Should Toilet/Shower be semi-private (4 per unit) or community?
Should smaller staterooms (minimum allowed by regulations) be used to gain more berths if needed?
|
||||||||
Comments on Berthing SMR
|
||||||||
Working Deck Space |
Published Requirement |
|||
Working deck related issues that directly impact vessel size and cost:
|
Working deck area: 1,000 sq ft minimum clear area aft of deck houses; desirable 1,500 sq ft. Additional contiguous minimum 50' x 10' area along one side for coring, etc. Total amount of clear working area available on the aft main deck should be at least 1,300 sq ft. | |||
A spacious stern working area with 1,000 sq ft minimum aft of deck houses open and as clear as possible from one side to the other is required. In addition, a contiguous waist work area along one side (starboard preferred) that provides a minimum of a 50 ft length of clear deck along the rail should be available. This area will allow for 10 to 15 meter piston coring and other operations. A minimum width of eight feet is needed for the coring operations and the overall width of the waist deck should be wide enough to accommodate all planned operations. The total amount of clear working area on the main deck aft should be maximized and equal at least 1,300 sq ft. It is desirable to accommodate at least a 10 meter (33 ft) core and up to 15 meter (50 ft) piston coring operations. The coring process design and design for other major operations should take place during the early design of the vessel. There should be space for up to two vans on the main deck with minimal interference with over the side operations. A clear foredeck area should be capable of accommodating small, specialized towers, booms, and other sampling equipment as much as possible. Providing tie down sockets, power, water, and data connections will facilitate flexible use of this space. Additional deck areas should be provided with the means for flexible and effective installation of incubators, vans, workboats, and temporary equipment. |
||||
QuestionsWhat is the minimum required clear deck space on the main deck? Is 50 ft of deck space along the rail required? (answer no if you think it can be reduced)
What should be the minimum number of van spaces? Do both van spaces have to be on main deck?
|
||||
Comments on Working Deck SMR
|
||||
Lab Space |
Published Requirement |
||
Lab Space related issues that directly impact vessel size and cost:
|
Laboratories: Total lab space should be a minimum of 1,000 sq ft (1,500 sq ft is desirable) including:
|
||
QuestionsWhat is the minimum required lab space? Do all labs have to be on the Main Deck?
Comments on Lab Space SMR
|
The majority of the lab space should be located in one or two large lab(s) that can be reconfigured, partitioned, and adapted to various uses to allow for maximum flexibility. This flexibility is an important design criterion. To the maximum extent possible, labs should all be located on the same deck adjacent to each other and adjacent to the main working deck areas. Labs should be designed to minimize their use as general passageways. Doors and hatches should be designed to facilitate installing large equipment, loading scientific equipment, and bringing equipment and samples to and from the deck areas. Doorsills should be temporarily removable. A total of at least 1,000 sq. ft. of lab space is required and 1,500 sq. ft. is desirable (dimensions below are approximate guidelines). On this class of vessel, the additional lab space may need to be provided in well designed and integrated laboratory vans in order to provide the flexibility in the amount of lab versus deck space available. The main (dry) lab area (up to 800 sq ft) should
be designed to be flexible with the provision for subdivision into smaller
specialized labs. An electronics/computer lab should be provided as a separate lab or as a defined area in the main lab. This space should be dry and separated as much as possible from sources of electronic noise. It may include a central watch standing space that should accommodate visiting science equipment as well as normally installed equipment. Provisions for remote displays in other labs should be part of lab designs. A separate electronics and equipment repair shop/work space for resident technicians that includes provision for repair bench space for visiting technicians is desirable. Storage space for resident technician spares and tools should be defined in the design so that it is not taken from useable laboratory space. A small separate room or partitioned space for IT (server, telephone, and network) equipment is desirable. High bay space for multiple purposes adjacent to the aft main deck is desirable. This space could support protected set up and repair of equipment, sample sorting, and other related functions. In this size vessel this function could be combined with the wet lab/hydro lab hanger space. A climate controlled workspace or chamber (approx. 100 sq ft) is required. This can be provided using a van or to some degree by providing a well-designed area that can be partitioned from the main lab or wet lab. If the vessel size or layout allows, the space might be provided as a separate lab space that can be used for other purposes as well. This space should be capable of controlling temperature to ± 0.5°C. Lighting should be controllable and programmable. Design of HVAC systems should be integrated with designed partitioning of laboratory spaces so that temperature control can be achieved. Access to labs should be designed to minimize effect on air-conditioning systems and climate control. Lighting control should also take into account partitioning plans Space for two (20 cu ft) stand-alone refrigerator/freezer units with similar configuration and refrigeration equipment capable of maintaining temperatures between - 15°C and 10°C (these temperature requirements should be verified during design) should be provided. Additional units (such as 80°C) could be accommodated at the expense of other uses of lab space or in van space when needed. Built in units should not be needed and should not be included unless the space could be used for alternate purposes when not needed as refrigerated space. |
Endurance |
Published Requirement |
|
Endurance related issues that directly impact vessel size and cost:
|
Endurance: 21 days; surge capacity 30 days (15 transit and 15 station) | |
| Endurance should be twenty one (21) days with a surge capacity for thirty (30) days endurance (15 days at cruising speed and 15 days station work, see station keeping and towing). Some mission profiles will require continuous underway survey or towing operations at speeds from 4 knots up to the normal cruising speed. It would be desirable for these vessels to have 21-day endurance for these types of cruises. The design process should consider the impacts on engines, water making capability, and other factors when on station or moving at slow speeds for extended periods of time. | ||
QuestionsWhat should the minimum endurance be? Is the ability to have a surge endurance of 30 days a high priority?
|
||
Comments on Endurance SMR
|
||
Range |
Published Requirement |
|
Range related issues that directly impact vessel size and cost:
|
Range: 8,100 nautical miles at optimal transit speeds
|
|
| An 8,100 nautical mile (15,000 km) total range is desirable at optimal cruising speed. | ||
QuestionsCan the range be reduced below 15,000 km
How much range is adequate for work from a regional vessel?
|
||
Comments on Range SMR
|
||
Speed |
Published Requirement |
|
Speed related issues that directly impact vessel size and cost:
|
Speed 12 knots; 10 knots sustainable through sea state 4; 7 knots in SS 5 | |
12 to 14 knots maximum speed at sea trial is desirable and at least 12 knots is required. Optimum cruising speed should be between 10 and 12 knots with 10 knots sustainable through sea state 4 (1.25 - 2.5 m wave heights). Speed control in sea state 3 or less (< 1.25 meters wave height)
should be Maximum speed and fine speed control should not be obtained at the cost of poor acoustical system operations, excessive noise, fuel consumption, or poor sea keeping. |
||
QuestionsDo you require more than 12 knots maximum speed?
What should the optimum cruising speed be? |
||
Comments on Speed SMR
|
||
Seakeeping |
Published Requirement |
|
Sea Keeping related issues that directly impact vessel size and cost:
|
Sea keeping: Ability to work in sea states 4 (1.25 - 2.5 m wave heights); >50% operational in SS 5 (2.5 - 4 m wave heights). | |
| Sea keeping is the ability to carry out the mission of the vessel while maintaining crew comfort and safety, and maintaining equipment operability. It is an important design criteria to maximize the sea-kindliness of these vessels and maximize their ability to work in sea states four and higher within the constraints of their overall size. It is desirable for these vessels to operate 50% of the time or greater in the wintertime in the Pacific Northwest and in the Northeast/Gulf of Maine. The use of bilge keels, anti-roll tanks or other methods to reduce the motions of these vessels should be incorporated in the designs. In sea state four (1.25 - 2.5 m wave heights) these vessels should be able to:
At sea state five (2.5 - 4 m wave heights), these vessels should maintain 7 knots and be capable of station operations 50% of the time. At sea state six (4 - 6 m wave heights), these vessels should maintain 4 knots and be capable of station operations 25% of the time. At sea state seven or greater (>6 m wave heights), these vessels should be able to operate safely while hove to. These motion criteria specifications should be verified as adequate and achievable during the earliest concept design phase. Otherwise, other motion criteria that result in ship motions that allow personnel and equipment to work effectively can be utilized during the concept design phase as long as the intent of the above sea keeping specifications is not sacrificed. Tables showing sea state and the practical effects of ship motion are included as appendices V and VI. |
||
QuestionsIs improved sea-keeping capability over the Cape Class a high priority?
|
||
Comments on Sea Keeping SMR
|
||
Assumes that choices will have to be made to meet cost and size constraints.
Within each group below; rank order the choices with 1 being the highest priority
1 |
2 |
3 |
|
| |
|
|
|
| |
|
|
1 |
2 |
3 |
|
| |
|
|
|
| |
|
|
1 |
2 |
|
| |
||
| |
|
First Name: Last Name:
Institution:
Email: