Ship Replacement (Renewal) Programming Thumb Rules
By Dick Pittenger (WHOI)

As we head down the road toward crafting a UNOLS modernization plan, it might be useful to have some idea about how much it will cost to buy and operate these craft and how long it will take. Here are some data points for your information.

HOW MUCH WILL IT COST TO BUY?

            Global ships                                                     $60M Ships always cost more than initial estimates.
    Examples:
                                                                    Estimate     Actual
ATLANTIS II                                     $3M             $5M
OCEANUS                                         *____         ____
NOAA FFRV40                                 $45M           $64M
AGOR-24/25                                      $38M           $52
KNORR/MELVILLE Conversion        $35M           $52M
AGOR-26                                            $45M           $54M+
CONNECTICUT                                 *____          ____
SMITH (RSMAS)                                *____           ____
BLUE FIN replacement (SkIO)             *____          ____
*Data not available
- Ten percent of construction costs should go into design (of first article); another
ten percent should be reserved for change orders.

HOW MUCH TO OPERATE? (per year)
 


THUMB RULES:

HOW LONG DOES IT TAKE? Large ships                                                             3 years
(Examples: AGOR-24/25, FFRV40)
Oceans Class                                                          2-2.5 years